§ 60-18. Zoning verification permit; certificate of compliance.  


Latest version.
  • (a)

    Zoning verification permit issuance; building permit required.

    (1)

    No structure of any kind, including a building, shall hereafter be erected, moved, or structurally altered or gravel pit, quarry or pond excavated until a building permit therefor shall have been applied for and issued. Issuance of a zoning verification permit shall not be deemed or construed to be a permit for, or an approval of, any violation of any of the requirements of this chapter. A zoning verification permit is issued, upon request, as verification of zoning status. Issuance of a zoning permit is not necessary when a building permit is issued consistent with applicable zoning.

    (2)

    All applications for a building permit shall be accompanied by a location sketch, showing the location, actual shape, and dimensions of the lot to be built upon, the exact size and location on the lot of the proposed or existing building and accessory building, the lines within which the building shall be erected, altered or moved, the existing or intended use of each building or part of a building, the number of families the building is intended to accommodate, and such other information with regard to the lot and neighboring lots or buildings as may be necessary to determine and provide for the enforcement of this chapter.

    (3)

    The lot and the location of the building thereon shall be staked out on the ground and inspected by the zoning administrator before construction is started.

    (4)

    Except as otherwise provided in this chapter, the zoning administrator shall issue or refuse to issue a building permit within ten days after receipt of an application therefor. Refusal to issue such permit shall be given in writing, with the reasons for such refusal.

    (5)

    Failure to obtain the appropriate permit before the start of construction shall be grounds for a penalty of double the permit fees.

    (b)

    Certificate of compliance.

    (1)

    No building hereafter erected, altered or moved shall be occupied until a certificate of compliance shall have been issued by the zoning administrator. Such certificate shall show that the building or premises or part thereof and the proposed use thereof are in conformity with the provisions of this chapter. Such certificate shall be applied for when application is made for a zoning permit and shall be issued within ten days after the completion of the work specified in such zoning permit application, but only if the building or premises and the proposed use thereof conform with all the requirements of this chapter.

    (2)

    Under such rules and regulations as may be established by the town board, the zoning administrator may issue a temporary certificate of compliance for part of a building.

    (3)

    Upon written request from the owner, the zoning administrator shall issue a certificate for any building or premises existing at the time of the original adoption of this chapter, certifying, after inspection, the extent and kind of use made of the building or premises and whether or not such use conforms to the provisions of the chapter.

(Code 2006, § 13-1-173)